Project Brief
We negotiated with our client and the engineer to complete preliminary piling works to establish likely driven lengths prior to commencing the main piling works on site. The site was a large open space; however, the area where the West Stand of the building would be constructed was situated close to the railway line, therefore, we implemented the use of our smaller Viking piling rig to drive the piles in this area.
Key Requirements
- Duration: 2 weeks
- Rig: Junttan PM20
- Piling System: Steel Tube
- Ground Conditions: Made Ground / Soft Clay / Gravel / Mudstone
- Number of Piles: 702 Piles total
- Pile Loads: Up to 550kN
- Pile Lengths: Up to 14m
- Testing Regime: Dynamic & Static