Scope of Works
Foundations and Residential

Project Overview

Green Piling worked with UK property developers Jomast, to deliver our Piling and Precast Ground Beam package for two residential development sites in Hartlepool.

Development Sites

Site A

  • 29 residential plots
  • 869m of G-sPan precast concrete ground beams
  • 189 No. 200mm square precast driven piles
  • 21 No. 250mm square precast driven piles
  • Pile depths ranging from 9m to 12m

Site B

  • 37 residential plots
  • 1,088m of G-sPan precast concrete ground beams
  • 142 No. 200mm square precast driven piles
  • 32 No. 250mm square precast driven piles
  • Pile depths ranging from 9m to 12m
A photograph of Green Piling G-sPan precast ground beam system

Key Requirements

To create a stable working platform and ensure the ground profile matched the final designs, this project required us to raise the site levels across both plots. Designed to meet the evolving needs of modern construction, our bespoke NHBC Accepts certified G-sPan precast ground beam system was the ideal foundation solution.

In addition to meeting both client briefs and safety requirements, we chose this method to:

By manufacturing the beams in-house with strict quality control, not only did we eliminate the need for extensive excavation, shuttering and concrete associated with traditional trench fill foundations, but we also produced efficient production timelines.

Close up shot of G-sPan precast ground beams with a Green Piling van in the background

Site Challenges

The project presented several challenges that required careful planning, design and collaboration from the outset.

Our Approach

Green Piling’s capability to produce stronger foundations around the UK is further strengthened by our bespoke design software, dedicated in-house design team, contract and site teams along with our own setting out engineers, enabling tailored solutions for each project and seamless collaboration from concept through to completion.

To reassure stakeholders and residents, Green Piling produced detailed risk assessments and supporting documentation to demonstrate how piling operations could be carried out safely within the vicinity of the railway infrastructure.

Residential G-sPan precast ground beams in a housing development

Delivery & Execution

Key Requirements:

Key Outcomes

The Hartlepool piling works were completed in just 17 days, with ground beam installation completed in 46 days, resulting in a total site duration of 51 days

 

Thanks to regular communication and our team of experts, the project was successfully completed ahead of schedule and delivered within budget. Here’s what that meant for the installation:

The successful completion of both developments demonstrated Green Piling’s ability to deliver efficient, cost-effective and compliant residential development foundation solutions in challenging environments, whilst meeting client objectives and maintaining high safety standards throughout.

Residential G-sPan precast ground beam foundations in Hartlepool

Looking for piling expertise for your residential or commercial development project?

Green Piling takes pride in providing commercial and residential developments with stronger foundations across the UK. With our innovative methods and reliable team of experts, we get the job done right.

Get in touch today to get more information about partnering with us.

Share this post

Talk to a foundation expert

Get in Touch today to learn more about how our team can support.

    Let’s build strong foundations together

      Project Overview

      Green Piling worked with UK property developers Jomast, to deliver our Piling and Precast Ground Beam package for two residential development sites in Hartlepool.

      Development Sites

      Site A

      • 29 residential plots
      • 869m of G-sPan precast concrete ground beams
      • 189 No. 200mm square precast driven piles
      • 21 No. 250mm square precast driven piles
      • Pile depths ranging from 9m to 12m

      Site B

      • 37 residential plots
      • 1,088m of G-sPan precast concrete ground beams
      • 142 No. 200mm square precast driven piles
      • 32 No. 250mm square precast driven piles
      • Pile depths ranging from 9m to 12m
      A photograph of Green Piling G-sPan precast ground beam system

      Key Requirements

      To create a stable working platform and ensure the ground profile matched the final designs, this project required us to raise the site levels across both plots. Designed to meet the evolving needs of modern construction, our bespoke NHBC Accepts certified G-sPan precast ground beam system was the ideal foundation solution.

      In addition to meeting both client briefs and safety requirements, we chose this method to:

      By manufacturing the beams in-house with strict quality control, not only did we eliminate the need for extensive excavation, shuttering and concrete associated with traditional trench fill foundations, but we also produced efficient production timelines.

      Close up shot of G-sPan precast ground beams with a Green Piling van in the background

      Site Challenges

      The project presented several challenges that required careful planning, design and collaboration from the outset.

      Our Approach

      Green Piling’s capability to produce stronger foundations around the UK is further strengthened by our bespoke design software, dedicated in-house design team, contract and site teams along with our own setting out engineers, enabling tailored solutions for each project and seamless collaboration from concept through to completion.

      To reassure stakeholders and residents, Green Piling produced detailed risk assessments and supporting documentation to demonstrate how piling operations could be carried out safely within the vicinity of the railway infrastructure.

      Residential G-sPan precast ground beams in a housing development

      Delivery & Execution

      Key Requirements:

      Key Outcomes

      The Hartlepool piling works were completed in just 17 days, with ground beam installation completed in 46 days, resulting in a total site duration of 51 days

       

      Thanks to regular communication and our team of experts, the project was successfully completed ahead of schedule and delivered within budget. Here’s what that meant for the installation:

      The successful completion of both developments demonstrated Green Piling’s ability to deliver efficient, cost-effective and compliant residential development foundation solutions in challenging environments, whilst meeting client objectives and maintaining high safety standards throughout.

      Residential G-sPan precast ground beam foundations in Hartlepool

      Looking for piling expertise for your residential or commercial development project?

      Green Piling takes pride in providing commercial and residential developments with stronger foundations across the UK. With our innovative methods and reliable team of experts, we get the job done right.

      Get in touch today to get more information about partnering with us.