Project Brief
In 2018 we installed over 1300 Steel tubular piles in Seal Sands for Conoco Phillips. Main piling works were completed in one continuous operation using up to 3 rigs. Reclaimed/surplus steel tubular sections were used throughout with material testing undertaken on 1 in every 30 tube sections to demonstrate conformity with the clients specification.
Key Requirements
- Duration: Jul - Sept 2018
- Rig: 3 Rigs - Junttan, PMX20, PM20
- Piling System: Driven Steel Tube
- Ground Conditions: Tidal Flat Deposits, Overlying Glacial Till and Mudstone
- Number of Piles: 1331 Piles total
- Pile Loads: 735kN
- Pile Lengths: Up to 37m
- Testing Regime: 3no Preliminary Static Loads Tests. Dynamic Testing to 3% of Working Piles