Project Brief
This site previously housed a bakery, following demolition of this building, it was apparent that additional retaining walls were required to extend the basements onto the new building line. An agreed sequence of works was critical as both piling and excavation levels varied significantly across the site. Green Piling installed the main retaining wall plus two smaller retaining walls and bearing piles during a 4 week programme.
Key Requirements
- Duration: 3 weeks
- Rig: Soilmec 312
- Piling System: CFA
- Ground Conditions: Chalk
- Number of Piles: 140 Piles total
- Pile Loads: 350kN
- Pile Lengths: Up to 13m
- Testing Regime: Integrity