Project Brief
Green Piling designed, supplied and installed steel sheet piling to form a 16.2m long retaining wall to reduce the angle of a slope near a conveyor system and to differentiate between the graded heap and the sand and gravel fill upon which the conveyor stands. The installation of the sheet piling was designed to retain loose sand at a 30° slope with no surcharge on the basis that the foundations of the conveyor were adequate.
Key Requirements
- Duration: 1 week
- Rig: Junttan PM20
- Piling System: Sheet Piles
- Number of Piles: 27 Piles total
- Pile Loads: N/A
- Pile Lengths: N/A
- Testing Regime: N/A