Cemex UK hired us to update their Piles, to make way for a new Cement Grinding Plant.
Scope of works
Steel Tubular Piling

Project Brief

Green Piling installed Steel Tubular piles for a new cement grinding plant at Tilbury Docks. The piling works took place close to an existing building and inside a restricted access building where partial removal of the roof was required to enable the leader of the piling rig to be erected for the internal works. The piles were designed to a driven length of 25m using 12-14m length piles with interference mechanical joints.