Project Brief
Green Piling carried out the installation of serval mezzanines for the Range over varying locations using a mix of mini piles and precast concrete piles. Due to time constraints multiple rigs were used in some sites so the project could be completed before the Christmas period. If required sites also had pre-boring to ensure obstructions were removed to enable the project to be completed on time.
Key Requirements
- Duration: Sept - Nov 2010
- Rig: D1000
- Piling System: Steel Tube & Precast Concrete
- Ground Conditions: Concrete Mixture
- Number of Piles: 86 Piles total
- Pile Loads: Up to 220kN
- Pile Lengths: From 5m - 20m
- Testing Regime: Dynamic