Project Brief
In advance of the main piling we carried out a programme of trial bores and preliminary test piles, the results of which informed the design submission for the main works. The main works consisted over 430nr x 600mm diameter CFA piles (compression loads ranging 500KN to 2000KN [600KN tension / 100KN horizontal load] for 432nr apartments over two blocks. Other works including tower crane piles and additional load testing to working piles.
Key Requirements
- Duration: Feb - Apr 2022
- Rig: Soilmec SF65
- Piling System: CFA
- Ground Conditions: Tidal Flat Deposits-Clay, Silt And Sand
- Number of Piles: 407 Piles total
- Pile Loads: Up to 900kN to 2060kN
- Pile Lengths: 18m - 21m
- Testing Regime: 100% Integrity Testing


