Over 3 separate visits, 210 piles were developed by Green Piling.
Scope of Works
Steel Tubular Piling

Project Brief

Green Piling undertook the installation of steel piles for a new bridge approach. Piles were installed over 3 separate Visits. The method & sequence was agreed between Green Piling and the Client to ensure works were completed on time and with reduced waste. The under piles were driven to 10-12m lengths before being welded to the appropriate extension pieces. Static testing was carried out before the extensions were added.

Key Requirements

Share this post

Talk to a foundation expert

Get in Touch today to learn more about how our team can support.

    Let’s build strong foundations together

      Project Brief

      Green Piling undertook the installation of steel piles for a new bridge approach. Piles were installed over 3 separate Visits. The method & sequence was agreed between Green Piling and the Client to ensure works were completed on time and with reduced waste. The under piles were driven to 10-12m lengths before being welded to the appropriate extension pieces. Static testing was carried out before the extensions were added.

      Key Requirements