Project Brief
Green Piling undertook the installation of steel piles for a new bridge approach. Piles were installed over 3 separate Visits. The method & sequence was agreed between Green Piling and the Client to ensure works were completed on time and with reduced waste. The under piles were driven to 10-12m lengths before being welded to the appropriate extension pieces. Static testing was carried out before the extensions were added.
Key Requirements
- Duration: 2 weeks
- Rig: Junttan PM20
- Piling System: Steel Tubes
- Ground Conditions: Made Ground / Alluvium / Glacial Till / Coal / Sandstone
- Number of Piles: 210 Piles total
- Pile Loads: Up to 1500kN
- Pile Lengths: 27m
- Testing Regime: Kentledge / Static