Project Brief
For the installation of over 1900 piles at Ideal Boilers in Hull we utilised our own precast concrete piles that are designed and manufactured directly at our manufacturing facility. We worked with Network Rail and the main contractor to ensure that piles were installed in accordance with safe working procedures including undertaking vibration monitoring.
Key Requirements
- Duration: Sept - March 2022
- Rig: Junttan PM20
- Piling System: Driven Precast Concrete
- Ground Conditions: Tidal Flat Deposits, Overlying Burnham Chalk
- Number of Piles: 1990 Piles total
- Pile Loads: 450kN Compression
- Pile Lengths: 14m - 18m
- Testing Regime: Dynamic Testing to 2.5% and 2no Static Load Tests