Offering G-sPan modular foundation systems, an efficient and economic solution for complex ground conditions.
Scope of Works
Precast Piling & G-sPan
Foundations

Project Brief

Persimmon Homes acquired the former Wardley Colliery and landfill site near Gateshead to develop 144 new homes.

Detailed site investigations highlighted variable ground conditions and a risk of settlement from former coal seams and landfill deposits. These complexities made traditional strip foundations unviable for parts of the development. Green Piling proposed a cost-effective, engineered solution to overcome these issues. 

Key Requirements

Results

245no. 200mm precast piles and 1126m of precast ground beams were installed delivering an efficient, risk-managed foundation solution ideally suited to the challenging ground conditions of this brownfield site. Green Piling’s innovative G-sPan system, manufactured in our own in-house facility, enabled rapid on site installation, minimised the need for excavation and reduced waste and disruption. 

Our approach delivered Persimmon Homes a fast, efficient and sustainable foundation solution compared to traditional measures, while significantly reducing costs and carbon impact.

Client testimonial

“We managed to overdeliver the original scope of the works programme through strong communication and flexibility offered by Green Piling. We have one final visit on the development and look forward to working with Green Piling on future projects”

Michael Graham, Commercial Director

Share this post

Talk to a foundation expert

Get in Touch today to learn more about how our team can support.

    Let’s build strong foundations together

      Project Brief

      Persimmon Homes acquired the former Wardley Colliery and landfill site near Gateshead to develop 144 new homes.

      Detailed site investigations highlighted variable ground conditions and a risk of settlement from former coal seams and landfill deposits. These complexities made traditional strip foundations unviable for parts of the development. Green Piling proposed a cost-effective, engineered solution to overcome these issues. 

      Key Requirements

      Results

      245no. 200mm precast piles and 1126m of precast ground beams were installed delivering an efficient, risk-managed foundation solution ideally suited to the challenging ground conditions of this brownfield site. Green Piling’s innovative G-sPan system, manufactured in our own in-house facility, enabled rapid on site installation, minimised the need for excavation and reduced waste and disruption. 

      Our approach delivered Persimmon Homes a fast, efficient and sustainable foundation solution compared to traditional measures, while significantly reducing costs and carbon impact.

      Client testimonial

      “We managed to overdeliver the original scope of the works programme through strong communication and flexibility offered by Green Piling. We have one final visit on the development and look forward to working with Green Piling on future projects”