Denaby Court, Conisbrough
Main Contractor:
Fulford Builders
Engineer:
Dossor Group
Sector:
Residential
Value:
£88k
Green Piling undertook design, supply and installation of steel tubular piles and concrete ground beams at Denaby Court, Conisbrough to form part of the foundations for a new housing development comprising of four apartment blocks.
Piled foundations were chosen due to concerns over groundwater entry and the stability of foundation excavations.
Piles were cut down using burning gear and where necessary a cutting wheel. The steel works for the beams were constructed on site. Pile testing was also part of the package.